Skip to content

How many square metres the NTC 4595 requires for your school

Put in the groups per year and out come the classrooms, the open areas, the green space and the school garden. The areas per pupil did not move between 2020 and 2025: what changed is where they are taken from, and that is the part that costs the contract.

School accommodation schedule

Preschool · 2.00 m² per pupil
Primary and secondary · 1.65 m² per pupil
Multigrade · 1.80 m² per pupil

657.5 m²

Classroom area (indoor) · 390 pupils

975 m²

Outdoor areas

The rest of the schedule is missing: toilets, administration and spaces of types B to F. Neither figure is the built area or the site area.

Classrooms
Preschool · 2 classrooms · 2080 m²
Primary and secondary · 10 classrooms · 35577.5 m²
Outdoor areas
Circulation, outdoor gathering space and planted areas · 2.5 m² per pupil975 m²
Of that, planted · at least 60 %585 m²
Of the outdoor area, under continuous planting of native or adapted species, school garden included · at least 30 %292.5 m²
Curricular outdoor areas · 0.7 to 1.65 m² per pupil273 m² a 643.5 m²
School garden, with irrigation water allowed for30 m²

Curricular outdoor areas are capped within the 2.5 m² per pupil: they are not added on top of the outdoor area, they come out of it.

Check first what did not change

It is the first thing a team needs to know before redoing anything, which is why it comes before the list of changes. If your schedule already complied, this part still stands.

  • The classroom areas per pupil: preschool 2.00 m², primary and secondary 1.65 m², multigrade 1.80 m².
  • The 2.5 m² per pupil for circulation, outdoor gathering space and planted areas.
  • The minimum 60 % of that outdoor area to be planted, half of which (30 % of the outdoor area) under continuous planting of native or adapted species, school garden included.
  • The school garden: a minimum of 30 m² up to 500 pupils, and 50 m² above that.
  • The effective-use percentages for each type of space: 80 % for types B, C and F; 90 % for A and D; 100 % for E.

And what did change

  • The table that gave the size of the site left the normative body of the standard. In 2020 Table 2 sat in chapter 4, which is normative; in 2025 it is Table A.1 of an informative annex that states its tables «are not for mandatory use». The area of a site can no longer be justified by citing a row.
  • Curricular outdoor areas were brought in, clause 5.3.6.3. The term does not appear once in the 2020 edition.
  • Car parking provision is delegated to local planning instruments. In 2020 the standard set one car space for every five cycle spaces, at 20 m².
  • Chapter 8 stopped being called «comodidad» and became «confort». If your tender document cites «comodidad visual, numeral 8.2», it is citing the old edition.

How binding it is

The NTC 4595 does not declare itself mandatory. What makes it enforceable on a public project is article 3 of Resolución 1349 de 2022, issued by the Ministry of Education, which places compliance among the categories that can be funded with Ley 21 de 1982 money or with national funds assigned to the Ministry. Decreto 1077 does not mention it once: the building permit does not require it.

Do not redo the site layout on hearsay. Before moving a block, ask for the clause that requires moving it.

We need to get a public project built.