Skip to content

How many boreholes, and how deep, the NSR-10 requires

Puts a number on the «get a soil survey» that usually comes without one. And flags what pushes up items that are almost never in the budget for a country house: the slope, the 10 % gradient and the retaining walls.

Minimum ground investigation

Include floors, basements, terraces and plant levels.

kN

Leave it empty if there is no calculated structure yet.

And the ground

3 boreholes, 6 m deep

low-category construction unit

How the category comes out
By number of levels · 2Low
By maximum column loadNo figure yet
The more onerous of the two governsLow
Total drilling, as an order of magnitude18 m

Without the column load this classifies by levels alone, and that is a provisional floor: once there is a calculated structure it has to be looked at again, because the more onerous of the two governs.

How it is counted

  • Counting storeys includes every floor, basement, terrace and plant level.
  • At least half the boreholes must fall within the footprint of the building on the site.
  • At least half the boreholes must reach the minimum depth; the engineer may require more depending on the foundation.
  • With basements or cuts, depth is measured from the bottom of the excavation; where fill is placed, from the original ground level.

Meeting the minimum does not release the engineer from making whatever additional boreholes their judgement calls for, and if they do not make them, they must set the recommendation down in writing in the report.

The study must be directed and signed off by qualified civil engineers holding a current professional licence, and those engineers must be able to show more than five years of experience in the geotechnical design of foundations (counted from the licence) or postgraduate study in geotechnics.

I have a plot and I want to build on it.

We check what the planning rules allow on your plot, what can be built and what it costs, before drawing anything. Then we develop the full project through to the drawings and the permit application with the curaduría (the licensed private office that issues building permits in Cali and other large Colombian municipalities; in smaller ones, the municipal planning office).