Skip to content
Amtrak · Richmond station stair, photo 1 of 8

Amtrak · Richmond station stair

A complete stair for the station, installed in a 72-hour window.

2024 to 2025   Richmond, California, USA

Project data

Code
ARI
Years
2024 to 2025
Location
Richmond, California, USA
Client
Amtrak
What the team did
Project management: design, procurement, logistics and installation, with site visits and supervision at critical stages
Value
USD 350,000
Installation window
72 hours
Status
Installed

Inspection and fabrication. The inspection took place in 2024; fabrication and construction, in 2025. The project was postponed twice.

72 hours. With a schedule that tight, there were 72 hours to bring in the materials, install the stair, clean up and leave. The job lost its supervisor and the management team took over field supervision. The deadline was met.

Before

The original stair, between the platform and the underpass.

Fabrication and installation

The stair in the shop and its installation within the 72 hours, with the yellow-striped treads.

Back to the projects table

Do you have a project to manage or supervise?

The team manages, supervises and assesses construction in Colombia, the United States and the Caribbean. Tell us what you need and we will reply within 24 hours.